The client is not named, and all data shown is illustrative.
See how it works.
Explore the workflow. Changes stay inside this example.
Site reportsLog out
● Online
← Reports
Multi-span greenhouse · Níjar
Date: 23/10/2026
ContactAna Pérez (site manager)
Call+34 600 000 000DirectionsOpens the map
Jobs in this report
Dig post holes
Quantity120pcs
Workers
Tension wire
Quantity340m
Workers
+ Add job
Photos1/10
Add photo
Save
Site reportsTodayOffice
Report calendar
Week of 19–23 October
Not started
In progress
Finished
Mon 19
Crew 1Roof repair · Campohermoso
Crew 2Insect netting · El Ejido
Tue 20
Crew 1Roof repair · Campohermoso
Crew 3Greenhouse Níjar
Wed 21
Crew 2Insect netting · El Ejido
Crew 3Greenhouse Níjar
Thu 22
Crew 1Plastic replacement · Vícar
Crew 3Greenhouse Níjar
Fri 23
Crew 1Plastic replacement · Vícar
Crew 2Insect netting · El Ejido
Crew 3Greenhouse Níjar
Crew 4New structure · La Mojonera
Extra jobs this week
Crew 1 · Sliding door repair2 hTo invoice
Crew 2 · Damaged netting replaced3.5 hTo invoice
The project
01
The situation
Crew leaders filled in a paper report when they finished a job and brought it back to the office in person. By then the job could already be closed and invoiced, so extra hours and extra jobs never reached the bill. Nobody could see which crew was on which site, and many planned reports never arrived at all. Lost billable work added up to a serious sum. Many sites have no mobile signal.
02
What Rootiq did
We worked with the client’s own team on the whole system: we designed and built the crew app end to end and connected it to the ERP, and their team built the office panel and the server side. Every report now arrives in the office as data, the same day, signed.
03
The key decisions
Make the report work without signal and send itself when coverage returns.
Show windy days in the planning calendar, so the office knows which work can go ahead.
Record extra jobs requested on site as their own report.
Collect both signatures on the tablet, so a finished report needs no paper.
04
What was delivered
A crew app for a shared tablet: tasks, quantities, workers, photos and signatures.
Reports saved on the device and sent automatically when there is signal.
Extra jobs recorded separately and sent to the office system.
05
Where it stands
Live since June 2026. Extra-job reporting was checked on the live system in August 2026, and crews have used it every day since October 2026. We don’t publish client figures.